Partnership Proposal
SET Ministry — Mega Church Campus
Seasonal End Time Ministry | Kampala, Uganda | Est. 2014
|
July 2026 |
|
 Worship |
 Congregation |
 Building |
 Conference |
|
|
|
Executive Summary
SET Ministry is a registered born-again Christian organization in Kampala, Uganda, operating since 2014 under the leadership of Pastor Ivan Kaneene. We are seeking strategic partnerships to fund a multi-purpose mega church campus comprising a 100,000-seat sanctuary and a 100,000-student Christian school.
The project spans 4 phases (2026-2033) with a total budget of $8,300,000. Phase 1 is active with a target of $800,000 by December 2027.
|
|
$8.3M
Total Project
|
$800K
Phase 1
|
100K
Seat Capacity
|
100K
Student School
|
|
Pastor Ivan Kaneene Founder & Lead Pastor
|
About SET Ministry
Rooted in the transformative truth of salvation through Jesus Christ, SET Ministry is dedicated to upholding biblical stewardship principles to nurture spiritual growth, facilitate impactful discipleship, and spread the Gospel through evangelism and compassionate community service.
- Weekly worship services and Bible study
- Evangelism & community outreach
- Children & youth ministry programs
- Women's empowerment initiatives
- 24/7 online radio ministry
- School fees & orphan sponsorship
|
|
 Community |
 Youth |
 Outdoor |
 Education |
|
Project Phases & Budget
Phase 1: Land & Foundation
Target: December 2027 | Status: Active |
$800,000 |
|
Phase 2: Sanctuary Structure
Target: June 2029 | Status: Future |
$2.5M |
|
Phase 3: Education Campus
Target: December 2031 | Status: Future |
$3.0M |
|
Phase 4: Full Campus Completion
Target: December 2033 | Status: Future |
$2.0M |
|
Total Project Budget |
$8,300,000 |
|
|
Phase 1 — Detailed Budget
25 line items across land acquisition, construction, and project management.
| Item |
UGX |
USD |
| Land Deposit |
200,000,000 |
$54,000 |
| Legal Fees |
37,000,000 |
$10,000 |
| Surveying & Titling |
11,000,000 |
$3,000 |
| Land Documentation |
7,400,000 |
$2,000 |
| Site Clearing |
37,000,000 |
$10,000 |
| Access Road |
22,000,000 |
$6,000 |
| Perimeter Fencing |
45,000,000 |
$12,000 |
| Security Gate |
12,000,000 |
$3,200 |
| Gate House |
15,000,000 |
$4,000 |
| Site Office |
12,000,000 |
$3,200 |
| Workers Sanitation |
8,000,000 |
$2,200 |
| Borehole & Water Tank |
60,000,000 |
$16,200 |
| Temporary Power |
18,500,000 |
$5,000 |
| Concrete Foundation |
200,000,000 |
$54,000 |
| Structural Steel |
300,000,000 |
$81,000 |
| Foundation Reinforcements |
185,000,000 |
$50,000 |
| Concrete Works Labor |
74,000,000 |
$20,000 |
| Roofing Materials |
222,000,000 |
$60,000 |
| Project Manager |
108,000,000 |
$29,200 |
| Site Foreman |
54,000,000 |
$14,600 |
| Skilled Workers |
180,000,000 |
$48,600 |
| General Labor |
108,000,000 |
$29,200 |
| Site Security |
21,600,000 |
$5,800 |
| Contingency Fund |
200,000,000 |
$54,000 |
| Project Insurance |
11,100,000 |
$3,000 |
| Phase 1 Total |
2,148,600,000 |
$800,000 |
|
 Ministry |
 Fellowship |
 Evangelism |
|
Projected Impact
|
100,000 Sanctuary Seats |
100,000 Student School |
50+ Jobs Created |
|
10,000 Parking Spaces |
Since 2014 Track Record |
4 Project Phases |
|
Multi-Currency Guide
All amounts shown in Uganda Shillings (UGX) with conversions. Rates as of July 21, 2026.
| Currency |
Rate |
Phase 1 ($800K) |
| UGX — Uganda Shilling |
1 = USh 3,705 |
USh 2,964,000,000 |
| USD — US Dollar |
1 = $1.00 |
$800,000 |
| EUR — Euro |
1 = €0.876 |
€700,800 |
| GBP — British Pound |
1 = £0.744 |
£595,200 |
| KES — Kenya Shilling |
1 = KSh 130 |
KSh 104,000,000 |
| TZS — Tanzania Shilling |
1 = TSh 2,550 |
TSh 2,040,000,000 |
| CAD — Canadian Dollar |
1 = C$1.37 |
C$1,096,000 |
* Exchange rates are approximate and may fluctuate. For exact conversions, visit your bank or currency converter.
|
4-Phase Vision — Multi-Currency
| Phase |
UGX |
USD |
EUR |
GBP |
| Phase 1 — Land & Foundation |
USh 2,964M |
$800,000 |
€700,800 |
£595,200 |
| Phase 2 — Main Structure |
USh 9,263M |
$2,500,000 |
€2,190,000 |
£1,860,000 |
| Phase 3 — Interior & Systems |
USh 11,115M |
$3,000,000 |
€2,628,000 |
£2,232,000 |
| Phase 4 — School Campus |
USh 7,410M |
$2,000,000 |
€1,752,000 |
£1,488,000 |
| Total Project |
USh 30,752M |
$8,300,000 |
€7,270,800 |
£6,175,200 |
* All conversions at approximate rate of 1 USD = USh 3,705. Actual amounts may vary.
|
Partnership Opportunities
Phase Sponsor Fund an entire project phase ($800K - $3M) |
|
Item Sponsor Sponsor specific construction items |
|
Recurring Partner Monthly or quarterly giving commitment |
|
Named Gift Name a room, wing, or facility in your honor |
|
|
|
|